The working hours westbound lane closure of Fair Lane from Denny’s will extend past Juvenile Hall beginning the week of September 26th.
This is a weekly update to the community regarding the Western Placerville Interchanges Phase 1B Project.
Construction began Tuesday, September 6th.
Prior Week:
>Demolition, including roadway excavation, continued into this week.
>Subgrade for the new curb, gutter, and sidewalk was prepared.
>Conduit installation for the street lights began later in the week.
Current Week:
>Complete conduit installation for the street lights.
>Finish subgrade for the new curb, gutter, and sidewalk.
>Begin placing AB for the new curb, gutter, and sidewalk.
Following Week:
>Finish placing AB and begin forming work for the new curb, gutter, and sidewalk.
>Concrete may be poured later in the week.
>Clearing, grubbing, and tree removal for the second stage of construction may begin later in the week.
Important Information:
>During the first stage of construction the westbound lane between Juvenile Hall and Denny’s will be closed during working hours.
>The second stage of construction will begin the week of September 26th and the westbound lane closure will extend past Juvenile Hall.
>Please note that starting October 3rd and lasting until the beginning of December, a portion of Fair Lane will be closed 24‐hrs a day for Stage 2 construction.
>Please adjust your travel routes accordingly. At least one driveway to each parking lot will be open at all times.
Contacts:
Jim Fisher, Resident Engineer R.E.Y. Engineers (916) 612‐7581 jfisher@reyengineers.com
Ryan Ruddick, Inspector R.E.Y. Engineers (707) 391‐7013 rruddick@reyengineers.com
Rebecca Neves, City Engineer City of Placerville (530) 642‐5250 rneves@cityofplacerville.org